LYB vertical submerged pump start and stop operation 1) Before using the LYB vertical submerged pump to pump the unit, the LYB vertical submerged pump should be started for about 20 minutes. After the oil temperature rises, open the unit suction valve. Pump the unit. Operation procedure and maintenance of LYB vertical submerged pump 1. LYB vertical submerged pump start and stop operation 1) Before using LYB vertical submerged pump to pump the unit, start LYB vertical submerged pump operation 20 After about a minute, after the oil temperature rises, open the unit suction valve to pump the unit. YJCB is a leading manufacturer specialized in providing non-stick carbon steel Bakeware in China. Nonstick Bakeware,Bakeware Tools,Carbon Steel Cake Mold,Silicone Soap Mold Yangjiang YJCB Trade Co., Ltd , https://www.cbprokitchen.com
2) When vacuuming the unit, the gas ballast valve should be opened to allow the oil vapor to evaporate in time; and the oil discharge port should be opened regularly to release the oil (20 minutes once).
3) During the operation, if the vacuum of the main engine is very poor, the pumping valve should not be opened too large or too fast in principle, otherwise the LiBr solution can be easily extracted from the pump.
4) The condensate at the bottom of the oil damper should be discharged in time to avoid entering the LYB vertical submerged pump and being damaged.
5) Before decommissioning, after shutting down the unit's exhaust valve, it should continue to run for 20 minutes to allow the oil vapor in the pump to fully evaporate to prevent corrosion inside the pump. 6) Only when it is confirmed that there is non-condensable gas in the unit, the LYB vertical can be started. The submerged pump pumps the unit.
7) It is strictly forbidden to vacuum the unit blindly to avoid damage to the LYB vertical submerged pump and damage to the vacuum of the main unit.
Second, LYB vertical submerged pump maintenance
1) Special oil must be specified using LYB vertical submerged pump, otherwise the pump's oil discharge performance will be degraded, Botaibang ultimate vacuum capacity will be reduced, and the service life of LYB vertical submerged pump will be shortened.
2) Regularly change the oil, observe the oil contamination through the oil sight glass, and replace the pump oil.
3) The oil level rises, or the oil color is milky white, indicating that the oil is emulsified. Unscrew the oil drain bolt at the bottom of the tank to release the emulsified oil or oil beads.
4) When the LYB vertical submerged pump is running, if the oil level of the pump oil is lower than the lower line of the red dot of the oil level mirror, the pump oil should be replenished immediately until the oil level is generated to the upper line of the red dot of the oil level gauge.
5) If the pump has not been started for a long time, the LYB vertical submerged pump should be jogged several times before the LYB vertical submerged pump is officially started to avoid damage to the pump due to excessive load when the pump is directly started.
6) If the LiBr solution enters the LYB vertical submerged pump due to misoperation, the contaminated oil and LiBr solution should be released immediately, and the LYB vertical submerged pump should be pumped several times to discharge the residual solution and gradually use a small amount of oil. Replace the wash until there is no solution.
Http://news.chinawj.com.CN Editor: (Hardware Business Network Information Center) http://news.chinawj.com.cn
High quality long-lasting nonstick inside and out, perfect for all of your baking needs.
Easy cleaning and maintenance, Can be used safely in the oven baking.
We hope to cooperate with more customers for mutual development and benefits.Buyers are welcome to contact us!