Ground photovoltaic power station construction process

The construction of large-scale ground power stations involves a wide range of operations and involves many personnel. The project manager needs to manage a large number of people, financial resources, and materials, and must coordinate work hours, equipment entry time, and fund payments to ensure that the project is on time and with good quality. The volume is completed.

The following is a summary of the work and process of a project manager with rich experience in the construction and management of ground-based photovoltaic power plants.

The first stage

Ready to work

Work 1: Preparation for the project department

Include recommended project manager, project department staff, project management plan review, grade 1 network plan preparation and review, project department backup calculation and application)

Work 2: Entry into the project department

With production and life preparation

Work 3: Sitong and Ping

Lutong, Dentsu, water, communications, site formation

Work 4: temporary construction

Work 5: Full Station Wall (Column) Construction

Including basic, wall or mesh installation

Work 6: Construction team entering and living area construction

second stage

Civil construction

Work 1: Work within the PV array area

Work 2: Work in booster area

The third phase

Output line and opposite end spacing construction

Work 1: Concrete Tower Foundation

Work 2: Rod and Tower Installation

Work 3: Line laying

Work 4: Peer interval device basics

Work 5: installation of peer equipment (including wiring)

Fourth stage

Electrical installation engineering

Work 1: Electrical Installation in the PV array area

Work 2: Electrical installation in the booster station area

Work 3: Secondary Equipment Installation and Wiring

Phase 5

Commissioning part of the construction

Work 1: Single unit commissioning

Work 2: Secondary equipment single debugging

Work 3: Quality inspection station acceptance and deficiencies

Work 4: Quality inspection of grid companies

Work 5: System debugging

Work 6: Acceptance by the grid company

Work 7: System Integration

Work 8: Transfer to Production Transfer

Work 9: Trial Run

Work 10: Defect elimination in the late phase of grid connection

Work 11: Data submission

Work 12: Transfer of spare parts

Work 13: Completed Procedures

Work 14: Post-sale Transfer Procedure

LED Strip Light

Led Strip Lights,Led Phyto Lamp Strip Light,Led Plant Grow Strip Lights,Led Light Strips Non-Waterproof

Shenzhen You&My Electronic Technology Co., Ltd , https://www.ymledtrade.com